By providing your contact information to Sandbridge Life Realty Group, your personal information will be processed in accordance with Sandbridge Life Realty Group's Privacy Policy. By checking the box(es) below, you expressly consent to receive marketing or promotional real estate communication from Sandbridge Life Realty Group in the manner selected by you. For SMS text messages, message frequency varies. Message and data rates may apply. Consent is not a condition of purchase of any goods or services. You may opt out of receiving further communications from Sandbridge Life Realty Group at any time. To opt out of receiving SMS text messages, reply STOP to unsubscribe. SMS text messaging is subject to our Terms of Use.

Thank you for your message. We will be in touch with you shortly.

Explore Our Properties
Background Image

One Line in a Navy Letter Decided How Sandbridge Finally Gets a Second Road

Nimmo Parkway Extension Phase VII-B
Pat Barton

Ask anyone who has lived in Sandbridge Shores through a strong south or south west wind what happens next, and the answer is always the same. You watch the low spots on Sandbridge Road, because that road is the only way off the island, and when it flood.

That has been true for longer than most residents realize. What changed in 2026 is not that the road finally got fixed. It's that the one workaround Sandbridge has quietly leaned on for decades, a Navy-controlled detour through NAS Oceana Dam Neck Annex, got formally taken off the table as a real solution. That single fact, buried in the environmental review paperwork, is the reason a road project that has been "under study" since the late 1960s actually reached a decision this year.

The road nobody thinks about until it isn't there

Sandbridge Road is roughly 5.4 miles of two-lane pavement with no shoulders, dropping straight into roadside ditches on both sides. According to the City of Virginia Beach's own project documentation, about 60 percent of that stretch sits within the 100-year base flood elevation, meaning three to five feet of water is enough to close it during storms fed by Back Bay's tributaries. It is, and has always been, the only public road in and out of the entire Sandbridge community.

When the road goes under or gets blocked by a crash or fallen tree, there is no second public route. There's an unofficial one: NAS Oceana Dam Neck Annex, the naval facility bordering Sandbridge to the north. Residents used to drive through it routinely before security tightened after 2001. Since then, it has functioned as an emergency-only detour, opened at the Navy's discretion, never guaranteed.

That discretion is exactly what changed the math this year. In the briefing materials the Commonwealth Transportation Board reviewed in February 2026, VDOT included a Navy letter stating the Dam Neck Annex access point should not be considered a permanent route for the Sandbridge community going forward. That's not a new restriction on your daily commute. It's the Navy formally closing off the option of treating its base as the community's long-term backup plan, which meant the city and VDOT could no longer design around an informal detour that might not be there when it's actually needed.

Two ways to fix it, and only one of them avoided people's driveways

Once the Navy's letter took the base off the table, planners were left comparing two real alternatives: extend Nimmo Parkway to create an actual second road, or rebuild the existing Sandbridge Road corridor to modern standards. The numbers explain why one alternative won decisively.

Nimmo Parkway Alternative

Sandbridge Road Alternative

Residential property acquisitions

0

12

Commercial property acquisitions

0

2

Wetland and stream impacts

Fewer

More

Right-of-way

Existing city-owned corridor

Requires new acquisitions

The Nimmo Parkway option follows a corridor the city already owns, extending the existing parkway roughly 1.9 miles from Albuquerque Drive to Sandbridge Road, with an 800-foot bridge crossing Ashville Bridge Creek. No homes, no businesses displaced. The Sandbridge Road alternative, by contrast, would have meant rebuilding the corridor people already live along, which comes with a dozen residential relocations attached. City Council endorsed the Nimmo Parkway Alternative on January 20, 2026, and the Commonwealth Transportation Board formally identified it as the preferred location on March 18, 2026.

Where the process actually stands as of August 2026

It's easy to assume "preferred alternative" means construction is imminent. It doesn't. Here's the sequence that's already happened, and what's still ahead:

  • May 23, 2025: FHWA published the Notice of Intent to prepare a formal Environmental Impact Statement, the step that kicked the two-year federal review clock into motion.
  • January 20, 2026: Virginia Beach City Council endorsed the Nimmo Parkway Alternative as the recommended preferred route.
  • January 20 to March 2, 2026: VDOT and the city held a combined virtual and in-person public hearing and comment period on that recommendation.
  • March 18, 2026: The Commonwealth Transportation Board officially identified the Nimmo Parkway Alternative as the project's preferred location.
  • Now through late 2026: According to the city's own project page, the Draft Environmental Impact Statement has been completed, and the next milestone is a public hearing on that draft, expected later this year. Coordination with the Nansemond Indian Nation on the environmental review is ongoing.

The FHWA's own notice states the NEPA process is anticipated to wrap up with a combined Final EIS and Record of Decision within two years of the May 2025 notice, which points toward spring 2027 for that milestone. That's the environmental sign-off, not a ribbon cutting. Anyone telling you a second road is a year or two from opening is getting ahead of the paperwork.

The part of the story that's older than most of Sandbridge's homes

What makes 2026 feel different is how long this has actually dragged. The corridor was first identified in 1967 as False Cape Parkway, added to the city's comprehensive plan the following year, and renamed Ferrell Parkway in 1978. The city authorized purchasing the right-of-way in 1989 and completed that acquisition by 1991. A 1999 corridor study recommended the Nimmo Parkway alignment, bridge over Ashville Bridge Creek and all, as the preferred fix. A 2003 study reached the same conclusion. It wasn't formally added to the city's Capital Improvements Program as Nimmo Parkway Phase VII-B until 2016.

Nearly sixty years of studies recommending the same basic fix, and the thing that finally forced a decision wasn't a new traffic count or a bigger budget. It was a federal agency, the Navy, declining to let its own property keep functioning as everyone's unofficial safety net. Once that option was gone on paper, the city couldn't keep treating the base gate as good enough.

What this actually changes for daily life in Sandbridge Beach

If you live in Sandbridge, every errand, school run, and hurricane evacuation still funnels onto the same two-lane road it always has. That doesn't change this year, and it won't change next year either. What's different now is that the alternative everyone quietly relied on for the worst days, driving through Dam Neck when Sandbridge Road went under, is documented as a non-permanent fix rather than a standing backup plan.

That matters most in two specific ways. First, it means the eventual second route, whenever it's built, follows the corridor with the least disruption to actual homes: zero residential acquisitions on the winning alignment. Second, it means the region's emergency planners now have a stated reason to stop counting on base access as anything more than an occasional courtesy, which should push the timeline for a real second route forward rather than let it drift for another decade the way earlier studies did.

For now, the practical advice hasn't changed. Keep an eye on Sandbridge Road conditions during heavy rain, know that a base detour is a possibility rather than a promise, and expect the next real milestone to be the Draft EIS public hearing later this year. If you want to track the process directly, the community page posts project updates as they come through, including newsletters straight from the Nimmo Parkway VII-B team.

Sandbridge residents have waited through a lot of studies that went nowhere. This is the first one with a Navy letter attached explaining why the old answer stopped being acceptable. That's worth knowing, whether or not you ever drive past the barricades yourself.